Pile Foundations and Drilled Pier Installation

Pile Foundations and Drilled Pier Installation

BC 1704.8, BC 1808.2.2

1704.8 Pile foundations. A special inspector shall be present when pile foundations are being installed and during tests. The special inspector shall make and submit to the commissioner records of the installation of each pile and results of load tests. Records shall include the cutoff and tip elevation of each pile relative to a permanent reference. A special inspector shall ver­ify that pile installation procedures are in accordance with Sec­tion 1808.